Piling Works Commence - The Bank
After a challenging start with an unexpected basements and obstructions which we couldn't odex through we're making good progress on the 17 No. 14m deep mini piles for the rear steel frame extension to the rear of the building.
This frame will square off the building to form the rear apartments and part of the Penthouse structure.
Renovation works to the facade with stone cleaning are progressing well and the new hardwood double glazed replacement sash windows are commencing this week.